|
Section -2 |
CAUSES OF FAILURES OF MAJOR
SUB-STATION EQUIPMENTS AND REMEDIAL MEASURES |
1. INTRODUCTION
This section briefly describes about the probable causes of failure of major sub-station equipment viz. Power Transformers, Reactors, Circuit Breaker, Instrument Transformers, Surge Arrestors etc. and remedial measures taken to prevent such failures.
2. POWER TRANSFORMERS
Power Transformers are vital links in the chain of components constituting a power system, the failure of which affect the supply of electric power to the consumers. Internationally, the transformers are found to be very reliable but in our country the failure rates are quite high. Failure analysis quotes a host of reasons behind the failure of power transformers. These may include abused operations inept maintenance, substandard techniques adopted during manufacturing, testing and commissioning, substandard input materials, inconsistency environment, design deficiencies, abnormal operating conditions, over voltages, system short circuits etc.
The main causes of failures of transformers in service (CIGRE Survey) is given below:
|
Cause |
% of cases |
|
Design |
36 |
|
Manufacturing problem |
28 |
|
Material defects |
13 |
|
Poor maintenance |
5 |
|
Lightning surges |
4 |
|
Short circuits |
2 |
|
Components |
% of cases |
|
Winding |
29 |
|
Terminal |
29 |
|
Tank and Di-electric fluid |
13 |
|
Magnetic Circuit |
11 |
|
Other accessories |
5 |
However the main causes of failure as pertaining to our country are given below:
Table
|
Causes |
% Failures |
|
Design defects |
35.7 |
|
Manufacturing problems |
28.6 |
|
Material defects |
13.1 |
|
Transport or storage problems |
1.2 |
|
In-correct maintenance |
4.8 |
|
Abnormal overload |
Less than 1 |
|
Over-fluxing |
1.2 |
|
Lightning |
3.6 |
|
External short circuit |
2.4 |
|
Loss of cooling |
1.2 |
|
Unknown |
7.1 |
However, The failures in power transformers can be broadly classified as:
Weakness
in specification, design / manufacturing deficiency
2.1 Weakness in specifications
Many a times, a customer specification is silent on the various aspects of site conditions such as loading pattern, over fluxing, over voltage conditions, various system parameters, environmental conditions. These are some of the aspects where care has to be taken at the time of drafting of technical specifications.
2.2 Failure due to defective design
Some of the failures due to defective design are listed in the table given below.
|
Cause |
Effect |
Remedial Measures |
|
Failure of yoke bolt in insulation |
Causes local short circuit in the lamination resulting in intense local eddy currents |
Insulated yoke bands preferred or yoke bolt insulation should be class B insulation or higher. |
|
High flux density in core |
Causes large amount of force at time of switching and repeated switching damage winding insulation |
Flux density should not exceed 1.9 Tesla at maximum operating voltage |
|
Narrow oil duct in winding |
Results in improper cooling and damages insulation |
Adequate duct from point of effective cooling |
|
Improper transpositions |
Results in more loss and more heating |
Adjust the transpositions so that all conductors should have equal reactance |
|
Inadequate clearance between phases |
May result in short circuit |
Provide adequate clearance as per the voltage class |
|
Clamping ring not properly designed |
May fail during short circuit condition |
Thickness of clamping ring should be designed such as to withstand short circuit forces |
|
Insufficient bracing of leads |
May fail during short circuit condition |
Strong supports are required for bracing of leads |
|
Radiators not properly designed |
Result in improper cooling causing higher temperature for oil/windings |
Proper calculation of radiators is necessary |
2.3 Failures due to manufacturing deficiencies
Transformer manufacturing is more a craftsmanship rather than the machine work. The reliability of the transformer depends on the quality of raw materials and the workmanship. There are certain steps to be taken at manufacturing stage so that apparently minus slips-ups at that stage do not get amplified in major defects later on in service. Some of the failures due to manufacturing deficiencies are listed in Table given below.
|
Cause |
Effect |
Remedial Measure |
|
Loose winding and improper sizing |
Result in interturn or interdisc short circuit |
Proper sizing for keeping winding under clamping condition |
|
Burrs on lamination |
Result in local short circuit and result in heating |
Burr free condition to be ensured by good manufacturing facility |
|
Burrs on spacers and blocks |
Result in damaging conductor insulation |
Burr free condition to be ensured by good manufacturing facility |
|
Bad brazed joints |
Damage the conductor insulation and winding may fail |
Adopt good brazing procedures |
|
Metallic parts left over during manufacture |
May cause partial discharge |
Better house keeping to ensured |
|
Insulation surface contamination |
Results in insulation failure |
Cleanliness to be ensured |
|
All metal components not earthed |
Partial discharge may start and oil quality may get affected |
All metal components are to be properly earthed and this is to be added in check-list |
|
Bad and porous welding of transformer tank |
Result in oil leakage |
Surface cleanliness to be ensured and adopt good welding procedures |
|
Improper drying process |
Winding and insulation are not fully stabilized due to moisture leading to failure |
Extensive drying and oil impregnation process should be strictly followed as per voltage class |
2.4 Failures due to deffective materials
The quality of material used also reflects on the life of the transformers. A rigid control of quality at all the successive stages of manufacture right from raw material to finished product will avoid the failure in transformers. Some of the failures due to defective material is listed in Table given below:
|
Cause |
Effect |
Remedial measure |
|
Sharp edges in copper conductors |
Produce partial discharge and damage the conductor insulation |
The surface finish should be smooth |
|
Improper conductor insulation |
Deteriorate under influence of high voltage stress and damage insulation |
Check the incoming conductor insulation and also no. of layers for conductor covering |
|
Poor oil quality |
Insulation failure |
Maintain BDV & PPM as per manufacturers recommendations |
|
Particles in oil held in suspension |
Temporary breakdown |
Maintain oil cleanliness |
|
Bare copper for connection |
Formation of oxidation and sludges |
Provide enamel coating or paper covering on bare copper |
|
Defective accessories
OLTC |
Results in transformer failure |
These accessories to be procured from well established supplier in view of high service reliability |
2.5 Adverse operating conditions
The life of a transformer is normally dependent on the life of insulation. During the normal operation of the transformer, the ageing process is also at normal rate. The rate of ageing is related to temperature, moisture content and duration of loading conditions. At temperatures more than 140ºC, the gas bubbles are formed as a result of insulation deterioration. These bubbles are of potential danger in the vicinity of high voltage stress zone. This can initiate electrical damage leading to breakdown.
Life expectancy of transformer will get diminished through inadequate protection while operating in the abnormal conditions such as:
Sustained
overload conditions
2.6 Improper maintenance practices
Poor/inadequate maintenance in the areas of oil leakage, oil quality, critical accessories such as tapchangers, bushings, protective instruments etc. will cause trouble in transformer. In addition to this, there are various trouble-shooting problems encountered in the field, such as moisture, oxidation, solid contamination, gas bubbles, overcurrent, overvoltage (transient or dynamic), over temperatures, short circuit (mechanical forces) etc., for which sufficient care should be taken to safeguard the transformer. Preventive maintenance is strongly recommended to improve the reliability of transformer.
Some of the reported failures for transformers have been attributed due to either of the following causes:
Failure
of the winding insulation due to short circuit stresses
Some of these failures are briefly described below:
2.7 Failure of HV, LV and Tertiary Winding due to Short Circuit and Surge Voltages
Safety margin of transformer with reference to short circuit withstand capability has been reduced widely. ISS stipulates a time of 2 seconds. The World Bank Specifications recommends a time duration of 1 sec. On account of the graded time discremination provided on the protective relays, which are essentially over current and earth fault relays. Bus faults are cleared after a time delay and many of the transformers have been found failing for bus faults or a nearby fault on feeder converting into a bus fault due to failure of feeder breaker to trip.
The tertiary winding provided on the power transformer are not adequately related to provide insulation to withstand surge voltages as also not rated for adequate short circuit stresses. Tertiary winding inter-turn insulation failures have been found to be due to transferred surges also. Based on investigations of failure of tertiary winding CBIP has already brought out research paper providing guidelines for protections to be provided on loaded tertiary. As per CBIP manual on transformers, provision of tertiary winding has now been deleted upto 100 MVA, 3 phase 3 limbed core type construction. Special precaution for protection of tertiary is necessary particularly in case of capcitive/reactive loading. Frequency of switching on/off of capacitor/reactor, distance of source from the transformer, design and location of gapless arresters are some of the important factors which have to be considered before loading of the tertiary. Failure of tertiary windings generally have been experienced because of:
Overstressing
and inadequate cooling
CBIPs technical report on causes of failure of tertiary windings and BHELs recommendations for protection of tertiary winding (Journal Vol. 3 No.1 of 1978) provides required guidelines on the subject.
The clamping arrangement provided on the transformer to contain the short circuit forces were not found to be adequate. In some cases, the interphase and phase to ground clearance of the leads were found to be less which resulted into flash over and damage of insulation due to vibration and displacement under short circuit current. Damage has taken place in some cases due to failure of insulating components eg., insulating cylinders, supports, permalli wood etc. The failure of joints have also been reported while handling short circuit current. A few cases of failure of transformer on lighting impulse have been reported inspite of protection provided by lightning arrestors.
Failure of the transformers have been reported on switching surges. The transformer failed, when it was being energized after a supply failure form upper substation on tripping of transformer on external faults. Operation of differential and bucholz protection took place tripping the transformer breaker and isolating the transformer. In a few cases, the transformers have failed where Polarisation Index (P1) of winding insulation had deteriorated to 1.1 or less inspite of moisture content in transformer oil remaining within limit upto 35 PPM & BDV 50 KV. Deterioration of P1 Index on sustained temperature on load needs to be specified and examined. In one or two cases, the substation earth resistence was found to be higher. This resulted into high voltages to be impressed at neutral end of the winding during phase to ground short circuit on feeder/bus. This caused failure of interturn insulation at neutral end.
2.8 Failure of magnetic circuits
There have been failure transformer due to overheating of core and core burning, failure of core insulation and core assembly getting used, slipping of stampings and coming in contact with tank bottom. To overcome the above problems separate provision for core earthing and core fixture earthing through bushings provided by transformer is being resorted to. This facilitates monitoring of core leakage current, if any, and in ascertaining that core is not getting multiple earth and also healthiness of core board insulation.
2.9 Failure of on-load tap changers (oltc)
On load tap changers are the second largest reason for trouble in power transformers after short circuit. The defects in OLTC are of the following type:
Burning
of transition resistance
Some of the common problems noticed in the OLTC compartment, selector/debetor switch are:
It
appears proper care for selecting current rating of the OLTC is not
exercised by the manufacturer. Factors for efficiency of operation
and over loading capability of transformer have to be accounted for
to arrive at design current rating. The selected current rating
normally should be one step higher than the calculated value. It
would be advisable if purchasers technical specifications do
not leave this option to the manufacturer and current/voltage ratings
are specifically stipulated.
Quality
and rating of transition resistors have been one of the main source
of problem in OLTC. Repeated incidences of burning of transition
resistors is an area which calls for serious attention from OLTC manufactures.
2.10 Failure of bushings
Condenser type bushings are sent with tip portion sealed and covered by porcelain rain shade. The bottom condenser portion is sent covered with wax coated cotton tape. In some of the transformers these transit tapes were found to have not been removed wqhile hoisting the bushings on the transformer. Over a period of service, the wax melted on contact with hot oil inside the tank and the cotton tape opened out and caused discharge inside the tank. It is better to dispatch bushings from works with bottom portion sealed in oil filled tanks to be removed at site at the time of erection to avoid moisture ingress.
2.11 Suggestions to reduce failures
From the foregoing discussion reasons for transformer failure could be attributed to various causes. Some of the possible corrective steps are enlisted herein, to reduce such casualty.
2.12 Improved design and manufacturing practice
By adopting CAD and better shop floor management, more reliable units could be manufactured to eliminate:
Poor
short circuit withstand capability
2.13 Improved testing method
Transformer should be simulated to actual service condition first by sequential testing and then passing necessary current which could result into temperature rise. Thereafter conduction of all high voltage application tests could bring out insulation weakness. Simulated short circuit test if necessary on scaled model and measurement of magnetic balance and magnetization current could reveal abnormality. A chart is included at Annesure 1, depicting testing sequence. Finally oil parameter could be recorded after completion of all the tests and compared with initial values.
2.14 Erection at site
By adopting strict pre-commissioning test and checks possible erection mistakes and omissions could be avoided. This list is enclosed at Annexure 2 and could be based on site experience.
2.15 Problems external to transformer
Load management
By adopting efficient load frequency management systems could be better controlled avoiding damages and transformer failure due to
Overloading
After every tripping of transformer whether manually or through protective relay, before recharging the tap switch should be manually operated to bring the same to No.1 position. After loading, the transformer tap could be changed to suit bus voltage requirement.
Failure of switchgear and battery
This could be avoided by periodic testing and using proper duty switch-gear and battery.
2.16 Sub-station layout
Layout
Whenever single phase units are installed it is essential to provide partition valves of adequate heights and strength to prevent collapse. This will minimize chances of fire extending to the other units.
Soak pit and drain pit
Provision may be made for the necessary soak pit and drain pit in the substation layout.
3. FAILURE OF CIRCUIT BARKERS
A circuit breaker is considered to have failed, when the breaker fails to operates after a command is given or unable to interrupt the arc or withstand a system voltage. CB failures have resulted in blasting of one or more of the following components:
interrupting
chambers
Besides the above, the failure of breakers could also be attributed due to following reasons:
Mechanical
failure of operating lever
3.1 Preventive Measures for Avoiding CB Failures
The type of failures that have taken place reveals that there is urgent need to improve manufacturing quality of various components besides, if effective condition monitoring checks are also carried out, failures could be identified at the incipient stage and corrective actions can be taken accordingly. However following areas are suggested for preventive measures.
Design/technical specification modification
The modification required to be done in the technical specifications are as follows:
Mechanical
Close Interlock wherever provided should be identical for CB
with PIR or without PIR in order to avoid mixing of operating drives
during erection and during O&M.
Stringent quality checks during manufacturing
To avoid failures of CBs due to manufacturing defects, it is required to introduce a stringent quality checks in the standard manufacturing plans. Following quality checks are suggested:
All
operating levers to be tested for ultrasonic and radiography.
Introduction of state-of-the-art condition monitoring checks during service
Following condition assessment techniques which have been discussed in detail in the section dealing with the maintenance techniques may be adopted.
Dynamic
contact resistance measurement
4. FAILURES OF INSTRUMENT TRANSFORMERS
4.1 Failure of CTs
Preliminary failure analysis of failed CTs have revealed that most of the CTs have failed due to pre-mature ageing of primary insulation. Besides, other probable reasons of failure have been attributed to high system parameters i.e. voltage and frequency, switching over voltages, lighting over voltages. To minimize the failure of CTs following tests/checks are suggested for carrying out at site.
Measurement
of tangent delta and capacitance
4.2 Failure of CVTs
Preliminary failure analysis of failed CVTs have revealed that main reasons of CVT failures are:
High
value of tan delta
Besides the above following problems were also observed in one make of CVT:
Snapping
of bellow connection
The only remedial measures suggested to avoid failures is to do the proper condition monitoring checks of CVTs at site.
5. FAILURES OF SURGE ARRESTORS
Analysis of failure of surge arrestors have revealed failures mostly due to premature degradation of ZnO discs. To minimize the failure of surge arrestors it is suggested that surge arrestors are monitored online for presence of third harmonic resistive current in the leakage current flowing through surge arrestors. Leakage current upto 500 micro Amp is generally considered within acceptable limits.
Annexure 1
Testing Sequence for Power Transformers
|
S.No |
Test |
AT Manufactuers Work |
While Commissioning |
During Maintenance |
|
1 |
Ratio |
Yes |
Yes |
Yes |
|
2 |
Winding resistance measurement (at all taps) |
Yes |
Yes |
Yes |
|
3 |
Insulation resistance and Polarisation Index |
Yes |
Yes |
Yes |
|
4 |
Polarity, vector group |
Yes |
Yes |
--- |
|
5 |
Separate source withstand voltage |
Yes |
--- |
--- |
|
6 |
Measurement of No. load losses |
Yes |
Yes |
--- |
|
7 |
Load losses and measurement of impedance (at all taps) |
Yes |
Yes |
--- |
|
8 |
Temperature rise test |
Yes |
Yes |
--- |
|
9 |
Impulse withstand test |
Yes |
--- |
--- |
|
10 |
Switching surge withstand test |
Yes |
--- |
--- |
|
11 |
Induced voltage withstand and partial discharge measurement |
Yes |
--- |
--- |
|
12 |
Measurement of iron losses (after all type tests) |
Yes |
Yes |
--- |
|
13 |
Measurement of insulation resistance and polarization index |
Yes |
Yes |
Yes |
|
14 |
Measurement of capacitance and tan delta of windings |
Yes |
Yes |
Yes |
Annexure 2
Check List for Transformer Assembly
|
|
The erection drawings and literature of the transformer is available at site |
Yes/No |
|
|
Checked and found all the component available at site as per drawing (there are no breakages and shortages) |
Yes/No |
|
|
Rinsed all the pipings, radiators, conservator etc. with 60 KV tested oil and blocked with dummy plates |
Yes/No |
|
|
Filtered the oil for 60 KV BD value and recorded in the erection register (with 22.5 mm gap on oil test kit) |
Yes/No |
|
|
Measured the insulation values of the HV, MV condenser type bushing (with a 5 KV megger) found more than 5000 M. ohms after removing coverings, wrappers etc. |
Yes/No |
|
|
Washed with hot oil (in case of other bushing of plain porcelain type) |
Yes/No |
|
|
Assembled the bushing, after fixing corona shield and removing links and bends in pull through leads, on the turret at proper incline |
Yes/No |
|
|
Complete assembly of HV, LV T&N bushing done correctly |
Yes/No |
|
|
Completed all piping work consrvator explosion vent, equalisr pipes etc. as per the drawing and filled with oil, Buchholz relay checked (3º -7º incline) |
Yes/No |
|
|
Filled radiator after washing individually and ensuring removal of blanking plates and free movement of butterfly valves both top and bottom |
Yes/No |
|
|
Measured IR values with temperature after filling of oil and compared with the test values received from the supplier and recorded in register |
Yes/No |
|
|
For drying out of transformer |
Yes/No |
|
a) |
Applied proper lagging around the transformer. Fire fighting equipments procured and kept at site |
Yes/No |
|
b) |
Filter machine cleaned and filled with the transformer oil |
Yes/No |
|
c) |
Filter connected with outlet into the conservator and inlet from the bottom tank |
Yes/No |
|
d) |
Filter heaters, switched on and the filter temp. maintained less than 60 degree C and filter vacuum maintained of 755 mm of mercury |
Yes/No |
|
e) |
Dehydration process for 7 days maintained oil temperature 60 degree C in the transformer (thermometer pockets filled with oil) |
Yes/No |
|
|
Filled the radiators with 60 KV BDV tested oil. Opened the bottom butterfly valves provided between main tank and the radiators after opening top air release valve to communicate with main tank |
Yes/No |
|
|
All gases released from different release points in order to ascending heights |
Yes/No |
|
|
HV, LV T Neutral earthing provided |
Yes/No |
|
|
Petroleum jelly applied in clamps and connectors in the transformer bushing studs and checked the tightness |
Yes/No |
|
|
Blue slicagel crystals of 2.5 to 4 mm size filled in breather. Breather filled with oil after removing bottom cup, transit protection cover, cork packing etc. |
Yes/No |
|
|
Removed blanking plates on explosion vent pipe and fixed diaphram |
Yes/No |
|
|
In case of transformers provided with thermo-syphon filter and air cell (pronol bag) breathing arrangement all precautions taken as per manufacturers recommendations |
Yes/No |
|
|
All air release points and other points thoroughly checked to ensure that there is no oil leakage |
Yes/No |
|
|
|||