Annex 3

Preventive Maintenance Schedule for Current Transformers

S. No.

Tasks assigned

Shut Down (SD) Or Without Shut Down (WSD)

Periodicity

A.

I R MEASUREMENT

 

 

a.

I R measurement (Pl. DAR)

SD

In case of requirement

b.

Measurement of Tand and Capacitance

SD

3 Yearly*

c.

Measurement of CT Secondary resistance

SD

In case of requirement

d.

Magnetization Chracteristics

SD

In case of requirement

e.

CT ratio test

SD

In case of requirement

f.

DGA and testing of other parameters of oil

SD

In case of requirement

g.

Thermovision Scanning of CT and Top dome

WSD

Yearly

h.

Checking of Bellow Expansion

WSD

Monthly

i.

Visual inspection CT for oil leakage and crack in Insulator etc.

WSD

Monthly

MARSHALLING BOX

 

 

a.

Checking of oil leakage

WSD

Monthly

b.

Checking of healthiness of gaskets

WSD

Monthly

c.

Checking of space heater & Illumination

WSD

Yearly

d.

Checking the tightness of all connections including earthing

SD

Yearly

e.

Cleaning of marshalling box and junction box

SD

Yearly

B.

VISUAL CHECKING OF EARTHING HF POINT

 

 

a.

Visual checking of earthing HF point (in case it is not being used for PLCC)

SD

Yearly

b.

Checking for any breakage or cracks

SD

Yearly

c.

Checking of oil leaks

WSD

Monthly

d.

Cleaning of CVT capacitor stacks and tightness of terminal connections

SD

Yearly

e.

Capacitance and Tand measurement CVT

SD

3 Yearly

f.

Measurement of voltage at metering points in control Room

WSD

Monthly

g.

Testing of EMU tank oil for BDV

SD

6 Yearly

h.

Thermovision Scanning of Capaacitor stacks

WSD

Yearly

MARSHALLING BOX

 

 

a.

Checking of spacer heater & Illumination

WSD

Yearly

b.

Checking and tightness of all connections including earth connections

SD

Yearly

c.

Clearning of marshalling box and junction box

SD

Yearly

d.

Checking of healthiness of gaskets

SD

Yearly

*First time after one year from commissioning and then once in every three years.