Annex 10 (contd..)

Preventive Maintenance Schedule for Protection Systems

S. No.

Tasks assigned

Shut Down (SD) Or Without Shut Down (WSD)

Periodicity

 

PLCC SYSTEM

 

 

 

Power supply measurements

SD

Yearly

 

Transmitter checks

SD

Yearly

 

Receiver checks

SD

Yearly

 

Checks for Alarms

SD

Yearly

 

Reflex test

SD

Yearly

 

BUS BAR PROTECTION

 

 

 

Primary injection test

SD

As per requirement

 

Protection stability and sensitivity checks (To be done whenever the protection AC circuits are disturbed like addition of new feeder

SD

As per requirement

*Includes Z1, Z2, Z3 and Z3 (reverse)

**Includes Z1, Z2, Z3 and Z3 (reverse)

Note: The tests listed under (A) and (B) above may be carried out with out a Line SD ensuring

i) Proper isolation of the relay under test

ii) The Other Main Protection of the Line is healthy and is in service